Question

Shoulder backing at the right edge: Bid item #21 shows 3,230 LF for the right edge shoulder backing. Typical cross section shown on detail 5 of C3.1 shows right edge shoulder backing on both Eastbound and Westbound sides of the road. Takeoff along the shoulder excluding wedge grind areas sums to a total of 6,273 LF (3,087 LF Eastbound and 3,186 LF Westbound). Should the bid item quantity be 6,273?

Answer

See Addendum #1 for revised quantity for bid item #21. It is revised to 6,373 LF. (3,220 SF for WB and 3,153 SF for EB).