Question

Return to RFP page

Question

The following are some questions regarding the application of temporary equipment: (1) Does the City have a proposed plan for the temporary heating and cooling or is the expectation for the contractor to propose a plan? (2) Are spot coolers an acceptable means of providing climate control in the facility for the duration of the project? (3) If the answer to question 1 is yes, will you provide a list of spaces requiring cooling and heating so that we can develop an estimate for the equipment required?

Answer

(1) The contractor is to propose a plan. (2) Yes, spot coolers are an acceptable means of providing climate control in the facility for the duration of the project. (3) The contractor is to propose a plan.