Question
The following are some questions regarding the application of temporary equipment:
(1) Does the City have a proposed plan for the temporary heating and cooling or is the expectation for the contractor to propose a plan?
(2) Are spot coolers an acceptable means of providing climate control in the facility for the duration of the project?
(3) If the answer to question 1 is yes, will you provide a list of spaces requiring cooling and heating so that we can develop an estimate for the equipment required?
Answer
(1) The contractor is to propose a plan. (2) Yes, spot coolers are an acceptable means of providing climate control in the facility for the duration of the project. (3) The contractor is to propose a plan.